STAGE 3-5, AUGUST 12, 2019

 
 

STAGE 1- EXCAVATION & FOUNDATION

  • Making the big ol’ hole where your home will go

  • Concrete and Steel reinforcement is laid for the foundation


STAGE 3- ROUGH MEP

  • Mechanical, Electrical & Plumbing Systems


STAGE 5- INTERIOR FINISHES

  • Window sills, doors, trim, cabinets, appliances, vanities, and counter tops are installed

 

STAGE 2- FRAMING & STEEL REINFORCEMENT

  • Wooden bone structure of
    the home

  • Hides under the electrical and plumbing systems


STAGE 4- DRYWALL

  • On the outside of insulation to make less noise and give stability


STAGE 6- FINAL WALKTHROUGH

  • Builder will familiarize you with home features and a punchwalk will be performed

 

Exterior- Continues to be trimmed out and brick is on site, but installation has not begun. Final drive aisle is being poured.

Front Building-
- Priming is complete through 103
- Tape, mud, and texture is in progress
- Hardwood is complete in 101-102, in progress 103.
- Tile is complete in 101, in progress 102

Rear Building-
- Electrical is complete in all units
- Draft stop is complete in all units
- Insulation is complete in 3 units.